Commitments and Contingencies |
6 Months Ended | |||
---|---|---|---|---|
Jun. 30, 2018 | ||||
Commitments And Contingencies Disclosure [Abstract] | ||||
Commitments and Contingencies |
Ship Construction Contracts
Project Leonardo will introduce an additional six ships with expected delivery dates from 2022 through 2027, subject to certain conditions. Each of the six Project Leonardo ships is approximately 140,000 Gross Tons with approximately 3,300 Berths. We have an Explorer Class Ship, Seven Seas Splendor, on order for delivery in the winter of 2020. This ship is approximately 55,000 Gross Tons and 750 Berths. We have one additional Breakaway Plus Class Ship, Norwegian Encore, on order for delivery in the fall of 2019. Norwegian Encore is approximately 168,000 Gross Tons with approximately 4,000 Berths. The combined contract price of these eight ships was approximately €7.2 billion, or $8.4 billion based on the euro/U.S. dollar exchange rate as of June 30, 2018. We have obtained export credit financing for six of the ships which is expected to fund approximately 80% of the contract price of each ship expected to be delivered through 2025, subject to certain conditions. Two of the Leonardo ships are confirmed orders expected to be delivered in 2026 and 2027, subject to financing (we refer you to Note 13— “Subsequent Event”).
In connection with the contracts to build these ships, we do not anticipate any contractual breach or cancellation to occur. However, if any were to occur, it could result in, among other things, the forfeiture of prior deposits or payments made by us, subject to certain refund guarantees, and potential claims and impairment losses which may materially impact our business, financial condition and results of operations.
Litigation
In the normal course of our business, various claims and lawsuits have been filed or are pending against us. Most of these claims and lawsuits are covered by insurance and, accordingly, the maximum amount of our liability is typically limited to our deductible amount.
Nonetheless, the ultimate outcome of these claims and lawsuits that are not covered by insurance cannot be determined at this time. We have evaluated our overall exposure with respect to all of our threatened and pending litigation and, to the extent required, we have accrued amounts for all estimable probable losses associated with our deemed exposure. We are currently unable to estimate any other potential contingent losses beyond those accrued, as discovery is not complete nor is adequate information available to estimate such range of loss or potential recovery. However, based on our current knowledge, we do not believe that
the aggregate amount or range of reasonably possible losses with respect to these matters will be material to our consolidated results of operations, financial condition or cash flows. We intend to vigorously defend our legal position on all claims and, to the extent necessary, seek recovery.
|