Commitments and Contingencies |
12 Months Ended | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Dec. 31, 2023 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Commitments And Contingencies Disclosure [Abstract] | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Commitments and Contingencies |
Ship Construction Contracts For the Norwegian brand, we have four Prima Class Ships on order, each ranging from approximately 156,300 to 169,000 Gross Tons with 3,550 to 3,850 Berths, with currently scheduled delivery dates from 2025 through 2028. For the Oceania Cruises brand, we have an order for one Allura Class Ship to be delivered in 2025. The Allura Class Ship will be approximately 67,800 Gross Tons and 1,250 Berths. The impacts of initiatives to improve environmental sustainability, modifications the Company has made to its newbuilds and/or other macroeconomic conditions and events have resulted in delays in expected ship deliveries in the past. These and other impacts could result in additional delays in ship deliveries in the future, which may be prolonged.
As of December 31, 2023, the combined contract prices, including amendments and change orders, of the five ships on order for delivery was approximately €5.8 billion, or $6.4 billion based on the euro/U.S. dollar exchange rate as of December 31, 2023. We have obtained fixed-rate export-credit backed financing for the ships on order which is expected to fund approximately 80% of each contract price, subject to certain conditions. We do not anticipate any contractual breaches or cancellation to occur. However, if any such events were to occur, it could result in, among other things, the forfeiture of prior deposits or payments made by us and potential claims and impairment losses which may materially impact our business, financial condition and results of operations. As of December 31, 2023, minimum annual payments for non-cancelable ship construction contracts with initial or remaining terms in excess of one year were as follows (in thousands):
Port Facility Commitments As of December 31, 2023, future commitments to pay for usage of certain port facilities were as follows (in thousands):
Other Commitments The FMC requires evidence of financial responsibility for those offering transportation on passenger ships operating out of U.S. ports to indemnify passengers in the event of non-performance of the transportation. Accordingly, each of our three brands is required to maintain a $32.0 million third-party performance guarantee in respect of liabilities for non-performance of transportation and other obligations to passengers. The guarantee requirements are subject to additional consumer price index-based adjustments. In addition, our brands have a legal requirement to maintain security guarantees based on cruise business originated from the U.K., and we are required to establish financial responsibility by certain jurisdictions to meet liability in the event of non-performance of our obligations to passengers from those jurisdictions. As of December 31, 2023, we have in place approximately £62.4 million of security guarantees for our brands as well as a consumer protection policy covering up to £107.9 million. The Company has provided approximately $1.5 million in cash to secure all the financial security guarantees required. From time to time, various other regulatory and legislative changes have been or may in the future be proposed that may have an effect on our operations in the U.S. and the cruise industry in general. Litigation Investigations In March 2020, the Florida Attorney General announced an investigation related to the Company’s marketing during the COVID-19 pandemic. Following the announcement of the investigation by the Florida Attorney General, we received notifications from other attorneys general and governmental agencies that they are conducting similar investigations. The Company is cooperating with these ongoing investigations, the outcomes of which cannot be predicted at this time.
Helms-Burton Act On August 27, 2019, million and, on January 23, 2023, the Company filed a notice of appeal from that judgment. On April 12, 2023, the Company posted a sufficient supersedeas bond with the court to prevent any efforts by the plaintiff to collect on the judgment pending the appeal. On June 30, 2023, the Company filed its opening appellate brief with the United States Court of Appeals for the Eleventh Circuit. On September 29, 2023, the plaintiff filed its answering brief responding to the Company’s opening brief in the Eleventh Circuit. We believe that the likelihood of loss related to this matter is reasonably possible but not probable at this time; therefore, no liability has been recorded. The ability to make such estimates and judgments can be affected by various factors including, among other things: lack of legal precedent, stage of the proceedings, legal uncertainties inherent within the litigation process, the availability of appellate remedies, and involvement of numerous parties. We continue to believe we have meritorious defenses to the Havana Docks Matter. However, if the plaintiff prevails in the final outcome of this matter, there may be a material adverse impact on the Company’s financial condition, results of operations and/or cash flows. lawsuit was filed against Norwegian Cruise Line Holdings Ltd. in the United States District Court for the Southern District of Florida under Title III of the Cuban Liberty and Solidarity (Libertad) Act of 1996, also known as the Helms-Burton Act. The complaint, filed by Havana Docks Corporation (the “Havana Docks Matter”), alleges it holds an interest in the Havana Cruise Port Terminal, which was expropriated by the Cuban Government. The complaint further alleges that the Company “trafficked” in the property by embarking and disembarking passengers at the facility, as well as profiting from the Cuban Government’s possession of the property. The plaintiff seeks all available statutory remedies, including the value of the expropriated property, plus interest, treble damages, attorneys’ fees and costs. After various motions challenging the sufficiency of plaintiff’s complaint were resolved and voluminous discovery was completed, both sides filed motions for summary judgment. On March 21, 2022, the court issued an order granting plaintiff’s motion for summary judgment on the issue of liability and denying the Company’s cross-motion for summary judgment. The court scheduled a trial on determination of damages only for November 2022. The plaintiff elected to seek what the court ruled to be its baseline statutory damage amount, which was the amount of the certified claim plus interest, trebled and with attorneys’ fees. Given this, there was no fact issue to be tried, and the matter was removed from the trial calendar. On December 30, 2022, the court entered a final judgment of approximately $112.9
Other
We were a party to a claim against a vendor which resulted in a verdict of approximately $159 million in favor of the Company in October 2022, for which the vendor filed a notice of appeal in February 2023. In December 2023, the Company and the vendor agreed to settle the claim and entered into a new comprehensive services arrangement with preferred rates. The favorable financial impact of these preferred rates will be recognized during the term of the 10-year arrangement as the services are provided. In the normal course of our business, various other claims and lawsuits have been filed or are pending against us. Most of these claims and lawsuits are covered by insurance and, accordingly, the maximum amount of our liability is typically limited to our deductible amount. Nonetheless, the ultimate outcome of these claims and lawsuits that are not covered by insurance cannot be determined at this time. We have evaluated our overall exposure with respect to all of our threatened and pending litigation and, to the extent required, we have accrued amounts for all estimable probable losses associated with our deemed exposure. We are currently unable to estimate any other potential losses beyond those accrued, as discovery is not complete nor is adequate information available to estimate such range of loss or potential recovery. However, based on our current knowledge, we do not believe that the aggregate amount or range of reasonably possible losses with respect to these matters will be material to our consolidated results of operations, financial condition or cash flows. We intend to vigorously defend our legal position on all claims and, to the extent necessary, seek recovery. Other Contingencies The Company also has agreements with its credit card processors that govern approximately $2.9 billion in advance ticket sales as of December 31, 2023 that have been received by the Company relating to future voyages. These agreements allow the credit card processors to require under certain circumstances, including the existence of a material adverse change, excessive chargebacks and other triggering events, that the Company maintain a reserve which would be satisfied by posting collateral. Although the agreements vary, these requirements may generally be satisfied either through a percentage of customer payments withheld or providing cash funds directly to the card processor. Any cash reserve or collateral requested could be increased or decreased. As of December 31, 2023, we had cash reserves with credit card processors of approximately $51.6 million, which includes $20.1 million recognized in accounts receivable, net and $31.5 million recognized in other long-term assets. During the year ended December 31, 2023, the Company received a return of cash collateral from one credit card processor of $500 million, which was previously classified as other long-term assets. We may be required to pledge additional collateral and/or post additional cash reserves or take other actions in the future that may adversely affect our liquidity. |